Fort Worth Fiber network
Owner & operator: Sprocket Networks
→ Build Scorecard (per-phase progress) → Progress Over Time (deduped + reconciliation) → Lasso Footprint (serviceability & coverage) → Stakeholder presentation view
Stakeholder presentation viewFull view ↗
— mi reported complete
of — mi planned (HLD design) · completed is vendor-reported, deduped trackers
Evidence-verified on map—
Vendor-reported, pending as-built—
City target sites
— / — sites conduit passed
0 sites connected — no building drops or lit fiber yet
Conduit passed — Not yet reached —
Stage from proximity to as-built network (evidence-verified).
Map layers
Completed
Permitted
Engineered
Planned (HLD)
96 ct
144 ct
288 ct
432 ct
Other / unresolved
Sizes per splice plan (pending city sign-off). Inventory: 96/144/288/432 only.
1‑Way
2‑Way
4‑Way
7‑Way
Designed fiber plant
Splice cases (planned)
Ring splice
Lateral splice
Tie-in / pass-through
Per Miguel’s splice plan — pending city sign-off. No fiber pulled or spliced yet.
Handhole (fill = stage color)
Handhole with field photos
Engineered & Permitted mileage = LIT program status. Completed = evidence‑verified. Map lines show geometry digitized so far.
Reconciliation tier
Vendor-reported progressDeduped contractor trackers · by phase
0–33%
34–66%
67–89%
90–100%
Deduped contractor trackers — vendor-reported, not evidence-verified built.
ⓘ Vendor-reported vs evidence-verified — what's the difference?
Field docs owed
— permits claim — ft complete with no redline or as-built on file
Vendor-claimed footage with no redline/as-built submitted — this is why evidence-verified lags.
Provenance — contractor, permit #, agency, and dates — is attached to every feature and included in all exports. Prepared for the City of Fort Worth & NCTCOG.
Two ways to count "built"

Vendor-reported (this tier) — what the contractors' weekly trackers say is complete, per City permit, with cross-vendor double-counting removed (one permit handed Sunrise→Jacqueline is counted once, not twice). Shown shaded per phase because the permit-to-corridor link only exists for a handful of corridors; we attribute progress at phase level rather than guess which specific segment a permit's footage belongs to.

Evidence-verified built — the crisp green/colored conduit lines, drawn only where a digitized as-built, redline, or bore log confirms the geometry foot-by-foot. This is the slower, harder number and is usually lower than the vendor-reported figure (the gap is the as-built digitization backlog).

Both are shown so the difference is visible, never collapsed into one number. Full reconciliation and the weekly trend: Progress Over Time →

Stakeholder data export
Provenance — contractor, permit #, agency, dates — is attached to every feature and included in all exports.
⬇︎ Shapefile ⬇︎ KMZ
⬇︎ Permit schedule (CSV) ⬇︎ Build scorecard (CSV) ⬇︎ Vendor-reported progress (GeoJSON)
Latest map updates
Conduit most recently added to the map from digitized redlines & as-builts.
Construction progress — Fort Worth Fiber
Completed network only · Jan 2025 → today
Today
— ⓘ