Vendor-reported (this tier) — what the contractors' weekly trackers say is complete, per City
permit, with cross-vendor double-counting removed (one permit handed Sunrise→Jacqueline is counted
once, not twice). Shown shaded per phase because the permit-to-corridor link only exists for a
handful of corridors; we attribute progress at phase level rather than guess which specific segment a
permit's footage belongs to.
Evidence-verified built — the crisp green/colored conduit lines, drawn only where a digitized
as-built, redline, or bore log confirms the geometry foot-by-foot. This is the slower, harder number
and is usually lower than the vendor-reported figure (the gap is the as-built digitization backlog).
Both are shown so the difference is visible, never collapsed into one number.
Full reconciliation and the weekly trend: Progress Over Time →
Stakeholder data export
Provenance — contractor, permit #, agency, dates — is attached to every feature and included in all exports.